Westside - Enota Park

Located on the west side of Atlanta, Enota Park is an 8-acre park that will include a large lawn, boardwalk, overlooks, pavilion, seating area, half-court basketball, splashpad, play area, security cameras, guard rails, retaining walls, and separate bathroom and utility buildings.

Open lawn with curved paths rendering.

Project Status
  • Reeves Young and ABI had a construction kickoff meeting to begin preliminary submittal reviews and discuss logistics in preparation of construction starting construction.

  • Reeves Young will be fencing off the entirety of the limits of disturbance for site security. The current Lucille Avenue access point will have detour signage pointing people to use the new RDA access point for the duration of construction.

  • Construction is anticipated to start in early April with survey layout, followed by erosion control and fencing. The project construction schedule is expected to be approximately 23 months, with an anticipated completion date in early 2026.

Project Timeline

  • 2020: Design Completed

  • Early 2025: Expected Start of Construction

Design & Construction Team

Questions?

Meghan Injaychock
Senior Project Manager